Quick answer

Commissioning a wet underfloor heating system runs in five steps, in this order: pressure-test the loops before the screed, fill and vent one loop at a time, dry the screed on a stepped ramp, balance every branch to its design flow, then verify the thermostat-to-actuator chain and record it. Most cold-room callbacks come from skipping step four.

  • Test pressure: 1.5× working pressure, so a 2 bar system is proved at 3 bar
  • Supply water: 35–45 °C for screed; surface limit 27–29 °C
  • Actuator: 3–5 minutes to stroke, ≥4 mm travel, 2 W
  • Manifold rating: 16 bar / 110 °C, 12 Kv main (brass)

Commissioning is the part of a floor heating job that nobody prices. The pipe goes down, the screed goes in, the van leaves. Six weeks later the phone rings: the living room never gets there, the bathroom is fine, and could somebody come and look.

Usually nothing has failed. The system was never proved, vented, dried or balanced, and each of those omissions produces the same complaint in a different way.

Five commissioning checks in order: pressure test, fill and vent, screed ramp, balance, verify and record
Five checks, in order. Each one proves the one before it, which is why the sequence matters more than any single step.

The order below is the one that avoids the callback. It also produces a single sheet of paper you can hand over, which matters more than most installers think.

Prove the pipe before it disappears

The cheapest leak to fix is the one you find while the pipe is still visible. After the screed, the same pinhole is demolition.

Test above the working pressure. Most project specifications call for 1.5 times working pressure, so a domestic system running at 2 bar is proved at 3 bar. That is still far inside the 16 bar rating of the manifold, which is the point: the test is aimed at joints and pipe, not at the brass.

Two practical details decide whether the test means anything.

  • Hold the pressure long enough to see a slow drop, and leave the gauge in place. Twenty minutes proves nothing in 900 m of pipe.
  • Photograph the gauge with the date visible. A test you cannot evidence is a test that did not happen, and the screed contractor will ask.

Keep the loops continuous under the floor. No joints, no couplers, no “just this once” behind the kitchen island. Every buried joint is a future excavation, and the manifold is the only place a connection should be reachable.

Fill one loop at a time

Air is the most common “fault” in a new system. It blocks circulation as effectively as a closed valve, it makes the pump noisy, and it survives a lazy fill.

Fill properly: close every branch valve except one, open the fill point, and let the water push the air out of that loop and ahead of it. Then close that branch and open the next. Water pushing air works. Water circulating around air does not.

Vent at the manifold until the flow runs clear, then top the pressure back up, because venting costs water as well as air. Expect to do it again after the first few days of running. Cold water holds dissolved air, and heating it releases that air into the highest points of the system, which is rarely where you left the gauge.

Air at the pump is the same problem in a different place. Our guide to bleeding underfloor heating walks through the valve-by-valve sequence. Air through an impeller is noise first and wear second. If a newly filled system sounds like it is boiling, it is not boiling. It is cavitating or passing air, and the answer is at the manifold, not at the boiler.

Dry the screed on a ramp, not a switch

New screed must be fully cured before any heat goes into it. Heat too early drives moisture out faster than the slab can tolerate, and the shrinkage cracks that follow travel straight up into the tiles.

Once cured, the heat-up is a programme, not an event. A typical ramp starts around 25 °C supply, holds, then lifts in 5 °C steps with a day between steps. The number that governs is the one in the screed manufacturer’s data sheet, not a rule of thumb from a forum.

Screed heat-up ramp: hold at 25 °C, then 5 °C per day to a 45 °C design flow temperature
Typical ramp only. The screed manufacturer’s schedule governs, and the supply temperature at each step goes on the record.

Two reasons to keep the record.

First, warranty. Many screed and adhesive warranties require evidence that the ramp was followed, and that evidence is a table of dates and supply temperatures, not a memory of doing it.

Second, drift. The supply temperature you commission at becomes the baseline for every future service visit. When a room is cool in three years, the first question is whether the mixing valve is still delivering 40 °C or has quietly settled at 33 °C. Without the original figure there is nothing to compare.

Surface temperature is the limit that matters, not supply temperature. Occupied floors normally sit at 27 to 29 °C, with bathrooms a little higher. Supply water for a screed system is typically 35 to 45 °C. If a room cannot reach temperature at the correct surface limit, adding degrees will not fix it, because the output per square metre is already capped. The answer is insulation, not a higher setting.

Balance with the flowmeters, not the thermostat

Loops are never the same length. The branch nearest the manifold has the least resistance and takes more than its share; the longest loop gets what is left. The result is a system that is working perfectly and heating unevenly.

Balancing means setting each branch to the flow on the design, using the flow indicators on the manifold. Short loops get restricted so the long ones can breathe. It is not a matter of opening everything fully and hoping.

Two wrong responses are worth naming, because they are common.

Raising the supply temperature does not correct imbalance. It raises the temperature of the water that is already going the wrong way round the system.

Raising the pump speed does not correct it either. More pressure pushes more water through the easiest path first, which is the loop that was already too warm.

Balanced properly, most systems can run at a lower supply temperature than the one they were commissioned at, which is the entire economic argument for doing it on a heat pump.

“A perfectly specified manifold that nobody balances will still leave one room warm and one room cold, and the customer will blame the hardware. Flow meters are there to be used, not just to look reassuring inside a cabinet.”

— Maggie Shen, Director, Legom

Check the control chain, then write it down

The last check is electrical, and it takes ten minutes per zone. Set the thermostat high enough that the zone is genuinely calling. Measure voltage at the actuator terminals. If there is voltage and the valve has not moved after five minutes, the actuator is the suspect. If there is no voltage, the fault is upstream: thermostat, wiring centre, or base station.

M-B32 brass manifold with a 920018PL thermal actuator at the control point
The control chain ends here. Actuator on valve head, M30 × 1.5, three to five minutes to stroke.

Before condemning an actuator, press the valve pin with a thumb. A pin that moves freely and springs back means the actuator has failed. A pin that is stiff or immovable means the valve is scaled or stuck, and a new actuator will change nothing.

Three normal behaviours get replaced every week for no reason. Thermal actuators take three to five minutes to stroke, because wax has to melt. Many ship in the first-open position so the system can be filled and tested before the electrics are finished. And a floor at 28 °C feels lukewarm to a hand, not hot.

Then label. Every branch gets the room it serves, written on the manifold cover and on the handover sheet. An unlabelled manifold turns a five-minute service call into an hour of guessing, and the label costs nothing at commissioning.

The sheet worth handing over

Stage What to record Why it pays later
Pressure test Test pressure, hold time, photo of gauge, date Proves the loops before they are buried
Fill and vent Date, loops vented, top-up pressure Air is the most common false alarm
Screed heat-up Ramp dates, supply temperature at each step Warranty evidence and drift baseline
Balancing Flow per branch against design Prevents the one-cold-room call
Controls Thermostat-to-zone map, NC/NO, voltage, actuator model Halves diagnosis time on every later visit

Example commissioning record sheet listing loop, room, design flow, measured flow and supply temperature
Example layout, not project data. One page per manifold, photographed before the cabinet closes.

One page. Loop number, room, design flow, measured flow, supply temperature, actuator type, date. Photograph it and leave a copy in the manifold cabinet.

FAQ

What pressure should an underfloor heating system be tested at?

Usually 1.5 times the working pressure. A domestic system at 2 bar is tested at 3 bar. The manifold rating of 16 bar leaves plenty of margin, so the test is really proving the pipe and the joints. Follow the project specification where one exists, hold the pressure long enough to detect a slow drop, and record it.

How soon after the screed can the heating be switched on?

After the screed has fully cured, then on a stepped ramp rather than straight to the design temperature. Curing time depends on screed type and thickness, so the screed manufacturer’s schedule governs. Heating a green slab is one of the three classic causes of cracked tiles, along with missing movement joints and the wrong adhesive.

The loops are all similar lengths. Can balancing be skipped?

You can spend less time on it, but not none. Pipe length is only one source of resistance; bends, manifold port geometry and installation differences all contribute. Verify the flow indicators rather than assuming, and record what you measured.

Why is a brand new actuator sitting open before it has power?

Many thermal actuators are supplied first-open so the system can be filled, flushed and pressure tested before the electrical work is complete. Once powered, they close and behave normally. It is a feature of the commissioning sequence, not a faulty unit.

One room is still cold after balancing. What is the next check?

Press the valve pin with the actuator removed. Free movement points to the actuator; a stiff pin points to the valve. If the pin is free, check voltage at the actuator while the zone is calling, then confirm the branch flow indicator is showing flow at all. Air is the next suspect, then a blocked or kinked loop.

—